RENOVATION PROJECTS IN PROGRESS

 

Bunker Renovation – Phase 1 – Started 1.18.18

  • Remove Bunker past marsh on right side hole #1 COMPLETED
    • Native plant material by marsh to be planted
    • Bunker will be shaped and sodded
  • Remove Bunker short left of pond hole#2
  • Remove Bunker right side of hole #6 after water hazard COMPLETED
  • Remove Bunker short left of green hole#12 COMPLETED
  • Bunker right side green #15 COMPLETED
    • Reshape bunker, add sod and smaller
  • Remove Bunker short left green hole#16 with sod COMPLETED
  • Bunker along right side of green hole#16
    • Sod first area up to wash out
    • Bunker will start and end about 20 yards
  • Bunker short left hole#18 removed

 

Bulkhead Repairs – Started 1.24.18 COMPLETED

  • Anticipated complete date = 3 weeks COMPLETED
    • One week in fairway COMPLETED
    • Two weeks greenside COMPLETED
  • Temporary green located middle of fairway before marsh COMPLETED
    • Yardages and signage will be on tees COMPLETED
  • Repairing 60 feet in fairway and 80 feet around green COMPLETED

 

Tree Removal – Started 1.29.18 – 190 trees approximately 10 trees per day

[table id=7 /]

 

Repair cart path hole#12 – hole#13 – start date TBD

 

WE APOLOGIZE FOR ANY INCONVENIENCE AND THANK YOU IN ADVANCE FOR YOUR SUPPORT

 

ALL AREAS NOTED ABOVE WILL BE TREATED AS GUR DURING PLAY